Solid Sawn Hangers

Panel Hangers

FHD

Reference Series: PFDS24
The FHD26 hanger straddles the header and receives a joist from both sides.
Materials: 18 gauge
Finish: G90 galvanizing
Code Reports: View Code Report Table

Installation

  • Use all specified fasteners.
  • In panelized construction, installers are allowed to nail through both the sheathing and the hanger top flange with (1) 10d nail. The nail should be centered in the top flange and be no closer than 1/4″ from the back or front edge of the top flange.

Need Help or Have a Question? Contact Customer Service or Call 800-328-5934

Code Report Table

FHD26